Sewer upgrade complete for Barwon Heads region

The Barwon Heads sewer project has been completed on schedule, improving services across the Bellarine Peninsula’s south.

The Barwon Heads sewer project has been completed on schedule, improving services across the Bellarine Peninsula’s south.

The new pipeline will move sewage from Barwon Heads, Ocean Grove, Point Lonsdale, and Queenscliff to the Black Rock Water Reclamation Plant in Breamlea.

Barwon Water Managing Director Shaun Cumming thanked the local community for its understanding while the essential works were carried out.

“We appreciate the construction work and rolling traffic changes provided inconvenience, so we’re grateful for your support,” he said.

“This critical project ensures we can continue providing high-quality, affordable and secure wastewater services to the coastal communities.”

The upgrade of the sewer pipeline – between the Barwon River and Barwon Heads pump station – was required after a sewer leak in 2021.

A temporary sewerage pipeline, known as a bypass, was installed to ensure the network remained unharmed during construction.

Vegetation removal was avoided in the Village Park by weaving the bypass through the Village Park walking paths.

The sewer pipeline replacement was conducted in two stages, using a ‘lift and relay’ process.

‘Lift and relay’ occurs when part of an old pipe is dug out and removed, and a new pipe is laid in similar positions.

Barwon Water will continue to reinstate and maintain the work site over the coming months while new grass is established in the impacted areas.

This includes a new John Firth Memorial Garden, designed in consultation with the Firth Family.

Further information about the project can be found at www.yoursay.barwonwater.vic.gov.au/barwon-heads-sewer